|
Getting your Trinity Audio player ready...
|
With offshore wind power projects again on hold at the federal level, officials confirmed last week that contracts for the installations that Massachusetts hoped to bring online in the coming years will not be finalized until this summer, at the earliest.
Massachusetts selected 2,678 megawatts of offshore wind power spread across three projects in September 2024, kicking off contract talks that were expected to result in higher prices for power than past projects. The contract completion milestone has been delayed at least five times, and during the delay one of the selected projects has removed itself from consideration and another raised the potential for a multi-year delay.
The utilities negotiating contracts with the remaining projects informed the Department of Public Utilities in a Dec. 30 letter that they would not meet the Dec. 31 target for finishing contract talks, nor the Feb. 25 target date for contract filings.
The evaluation team involved in the process, which includes the Department of Energy Resources, National Grid, Eversource and Unitil, said delays are due “to ongoing uncertainty caused by federal level activities.”
The group said it now expects completed negotiations and executed contracts by June 30. Those contracts would now be filed with the DPU (the step at which ratepayers can learn the cost of the projects) by Aug. 31, putting the procurement process about two years behind its original schedule.
In a statement, the Healey administration blamed “uncertainty created by the changing federal landscape” for the repeated contract delays and said Massachusetts “remains committed to an all-of-the-above approach to energy, which includes offshore wind.”
“This abundant energy source produced right off our coast will lower costs, especially in cold weather, create thousands of jobs and billions of dollars in economic benefits for Massachusetts, and help move us toward energy independence,” said Lauren Diggin, spokesperson for the Department of Energy Resources.
Massachusetts state government has committed to reducing carbon emissions by at least 50% compared to 1990 baselines by 2030, by at least 75% by 2040 and by at least 85% by 2050, with tag-along policies to get the state to net-zero emissions by the middle of the century. The state also has numerous other mandates on the books, including those related to electric vehicles.
As a candidate for governor four years ago, Gov. Maura Healey made significant climate promises including achieving a 100% clean electricity supply statewide by 2030 and electrifying public transportation with clean power by 2040 (starting with school and MBTA buses by 2030).
As 2026 gets underway and Healey eyes her reelection effort, the House and Senate this session have become torn between reevaluating the costs of decarbonization plans and finding ways to reduce consumer utility bills.
The U.S. Department of the Interior’s order freezing offshore wind work affects the Vineyard Wind 1 project for Massachusetts, the only project currently under contract to provide power into the state. Vineyard Wind uses the Marine Terminal in New Bedford as its staging site.
The freeze also impacts Revolution Wind for Rhode Island and Connecticut, Sunrise Wind and Empire Wind for New York, and Coastal Virginia Offshore Wind off Virginia.
The developers of Revolution Wind, Empire Wind and Coastal Virginia Offshore have filed legal challenges to the Trump administration’s freeze, and the New York Times reported that officials behind Sunrise Wind have said they are contemplating the same.
A spokesman for Avangrid, one of the developers of Vineyard Wind 1, declined Monday to comment on the company’s plans.

Time to say goodbye to Healey and Wind forever.
SouthCoast Wind, formerly known as Mayflower Wind, initiated negotiations with the Town of Falmouth, Massachusetts, in 2019.
.
SouthCoast Wind backed out of the signed power purchase agreement and agreed in August 2023 to pay a $60.4 million penalty to Massachusetts utility companies (Eversource, National Grid, and Unitil) to terminate its Power Purchase Agreements (PPAs).
Postponed the first time. (1)
.
The SouthCoast Wind project’s Power Purchase Agreement (PPA) in Massachusetts has faced multiple extensions, with deadlines repeatedly pushed back from late 2024 through mid-2026.
November 2024 postponed again (2)
January 2025 postponed again (3)
March 2025 postponed again (4)
June 2025 postponed again (5)
December 2025 postponed again (6)
.
The new power purchase agreement is on June 30, 2026.
Time to say goodbye to Healey ……………. Wind is coming whether we like it or Not !!!!!!!!!!!!!
There only here because of the far left liberal government controlling our state, but by no means are they the answer to our energy needs. Healey loses, wind is gone, the wind companies won’t hang around, and that will be the best for the environment. Wind turbines in our waterways are an environmental disaster waiting to happen.
Wind power in Texas, a portion of total energy in Texas, consists of over 150 wind farms, which together have a total nameplate capacity of over 30,000 MW (as of 2020).[1][2] If Texas were a country, it would rank fifth in the world.
Texas has a Right Conservative, Straight, Christian Leadership.
The most recent major oil spill happened in 2003. On the afternoon of Sunday, April 27, a tank barge operated by the Bouchard Transportation Company passed on the wrong side of a navigational marker south of Westport. It struck underwater rocks, which gouged a 12-foot hole in the hull.
In total, 98,000 gallons of heavy #6 fuel oil spilled into Buzzards Bay. Oil washed up along 93 miles of coastline, clinging to rocks and marsh grasses. Hundreds of seabirds died, and beaches and shellfish beds were closed for months. Beautiful places like Barneys Joy in Dartmouth, West Island in Fairhaven, and Ram Island in Mattapoisett were some of the hardest-hit areas.
An environmental disaster waiting to happen, again.